Biomass to Electricity Project. Celulose Irani, Brazil





EEcoSecurities developed the Project Design Document (PDD) for the electricity generation from biomass proposal by Celulose Irani at the manufacturing plant that have in the Campina da Alegria district (State of Santa Catarina, Brazil). The aim was to reduce the proportion of electricity from the local network to minimize GHG emissions linked to the mains supply (with high weight of fuel oils). The proportion extracted from the overall grid was 44% (56% came from generation plants from existing biomass and small hydroelectric plants).



The project incorporated the construction of a biomass generation plant with a capacity of 9.43 MW, which would meet the growth in paper production (and derivatives). By burning waste wood chips and unused forest residue from the area, electricity was generated by a more energy-efficient process using technology that was safe for the environment and from paid for by the national bill. The raw material that resulted from the process had until then been treated as waste, which meant that its use guaranteed the reduction in methane generation, a by-product of the process of decomposition.



EcoSecurities was responsible for appraising the project for carbon credits (CERs) issued by definition to CDM (Clean Development Mechanism), and manage their sale via ERPA (CDM Emission Reduction Purchase Agreement).



The project's contribution to sustainable development was significant. At local level it supposed increased employment, and the national balance sheet included the promotion of clean technologies and the diversification of power generation sources in the country. This demonstration of the potential use of biomass as fuel favoured its adoption and the reduction of uncontrolled forestry landfills. At corporate level this allowed Celulose Irani to achieve its goals of cleaner production and respect the environmentally. The use of clean and efficient technologies and conservation of natural resources are part of Agenda 21 for Sustainable Development Criteria in Brazil.

PROYECTOS CAMBIO CLIMÁTICO

  • Proyecto

    Emissions rights portfolio assessment

    Emission rights strategy management for chemical group Soda Polska Ciech, Poland. [+]

  • Proyecto

    Cultivation Jatropha Gambia

    Pilot project for the extension of this woody species in desert areas through... [+]

  • Proyecto

    Climate Change Training

    IIMA developed and delivered this first Tecniberia course ‘Companies and Climate Change’ [+]

  • Proyecto

    Biomass to Electricity Project

    EcoSecurities were responsible for the process of obtaining CERs for a power generation activity… [+]

  • Proyecto

    Avoided deforestation Chaco, Argentine

    First project REDD in 45,000 ha of forest soil in the Argentine Chaqueño Park [+]

Consúltenos si desea saber más sobre nuestros proyectos en Cambio Climático.

Calculator

Calculator

CO2 Calculator

Calculate emissions from your activities and find out your carbon footprint.

More [+]

Consulting

Wine Industry Carbon Footprint

Pago del Vicario calculates the GHG emissions generated by the organisation and the production of PENTA red wine.

More [+]

Emissions Rights Management

EMISSIONS RIGHTS PORTFOLIO ASSESSMENT

Emission rights strategy management for chemical group Soda Polska Ciech, Poland.

More [+]

Ecosecurities

GHG emissions reduction

Sourcing, developing and trading emission reduction credits.

More [+]

AND ALSO...

    Jatropha cultivation in Africa

    Jatropha

    Pilot project for the extension of the jatropha cultivation for biodiesel manufacture.

    More [+]

    AT A CLICK

    REDD

    Avoided deforestation in Argentina

    Avoided deforestation project and supression of the causes of forest degradation.

    More [+]

    Proyects

    • Proyecto

      Almacenamiento Hidrocarburos Mallorca

      CLH encargó a IIMA Consultora la elaboración del EsIA de los nuevos tanques de almacenamiento en sus... [+]

    • Proyecto

      Gasoducto Almendralejo-Salamanca

      ENAGAS encargó a IIMA el estudio del gasoducto Almendralejo-Salamanca, con elaboración del EsIA y de la ATA. [+]

    • Proyecto

      Biomass to Electricity Project

      EcoSecurities were responsible for the process of obtaining CERs for a power generation activity… [+]

    • Proyecto

      Compressor Station Montesa (Valencia)

      ENAGAS solicitó a IIMA los trabajos de tramitación ambiental del proyecto de la Estación de Compresión de... [+]

    • Proyecto

      Explotación glauberita Toledo

      Carbones Pedraforca encargó a IIMA el Estudio de Impacto Ambiental del proyecto de una explotación a cielo... [+]

    • Proyecto

      Ordenación costa Almería

      Desarrollo de un ordenamiento sostenible en la costa de Pulpí (Almería) para hacer frente a la situación... [+]

    • Proyecto

      Legalización ambiental planta regasificación

      IIMA colaboró decisivamente en la elaboración de un estudio para la legalización ambiental de la planta... [+]

    • Proyecto

      El plumbismo en España

      IIMA estudió la incidencia del plumbismo en especies de aves cazables de zonas humedas, ante la aparición... [+]

    • Proyecto

      Medidas compensatorias gasoducto LIC

      IIMA elaboró las Medidas correctoras del gasoducto Córdoba-Santa Cruz de Mudela, cuyo paso por un LIC... [+]

    • Proyecto

      Asistencia técnica erosión Casa de Campo

      Estudio de la degradación de los suelos de la Casa de Campo, con identificación de las causas y... [+]

    • Proyecto

      Dispersión gases Aeropuerto Barajas

      IIMA elaboró el Estudio de Impacto Ambiental de la planta de cogeneración para abastecimiento de la... [+]

    • Proyecto

      Producción sulfato sólido férrico Huelva

      IIMA elaboró el Estudio de Impacto Ambiental de la planta de producción de sulfato férrico sólido de... [+]

    • Proyecto

      Estudio agrícola clementinas

      Estudio del comercio exterior de clementinas, incluyendo las variables y agentes implicados. [+]

    • Proyecto

      Vigilancia ambiental Puertomayor, Murcia

      La sociedad Puerto Mayor encargó a IIMA la Asistencia Técnica Ambiental del proyecto de puerto deportivo. [+]

    • Proyecto

      Gasoducto de la conexión con Francia

      ENAGAS encargó a IIMA el Estudio de Impacto Ambiental del gasoducto, con dificultad por el rechazo social y... [+]

    • Proyecto

      Asistencia integral gasoducto eje transversal

      Este Proyecto supuso un hito en cuanto a la cuantificación del impacto real en la fauna ocasionado por... [+]

    • Proyecto

      Climate Change Training

      IIMA developed and delivered this first Tecniberia course ‘Companies and Climate Change’ [+]

    • Proyecto

      Norma 352R1 Expedientes Declaración Impacto Ambiental

      Elaboración de la Norma 532 para la Evaluación de Impacto Ambiental en proyectos desarrollados por la... [+]

    • Proyecto

      Almacenamiento subterráneo GN Serrablo

      ENAGAS encargó a IIMA los estudios necesarios para la obtención de Autorización Ambiental Integrada de las... [+]

    • Proyecto

      Trabajos de reforestación

      IIMA ha realizado diversos trabajos de reforestación en condiciones exigentes para la consecuención de... [+]